Overview of Overseas Production Affiliates
Europe
TPCA
Panoramic view
Overview
Company name
|
Toyota Peugeot Citoroen Automobile Czech, s.r.o.
(TPCA) |
---|---|
Start of production
|
February 2005
|
Site area
|
1,200,000 m2
|
Business activities & products
|
Vehicle production: Aygo, Peugeot 107, Citroen C1
|
Production results for 2011
|
270,000 vehicles (including 91,000 vehicles of Toyota Aygo)
|
Number of employees*
|
3,030
|
Equity participation
|
TMC: 50%
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
2002
|
January
|
Joint venture agreement entered into with PSA Peugeot Citroen S.A.
|
March
|
Company established
|
|
April
|
Ground-breaking ceremony conducted
|
|
2003
|
April
|
Framework raising ceremony completed
|
2005
|
February
|
Ceremony marking the start of production conducted
|
May
|
Plant opening ceremony conducted
|
|
June
|
Sales partially commenced
|
|
October
|
Three-team, two shift labor system commenced
|
|
2006
|
January
|
Full operations commenced; Yearly production level of 300,000 vehicles
|
2008
|
November
|
Cumulative production reaches 1 million units
|
December
|
Aygo partially redesigned
|
TMMF
Panoramic view
Overview
Company name
|
Toyota Motor Manufacturing France S.A.S.
(TMMF) |
---|---|
Start of production
|
January 2001
|
Site area
|
2,330,000 m2
|
Business activities & products
|
Vehicle production: Yaris
|
Production results for 2011
|
150,000 vehicles
|
Number of employees*
|
4,430
|
Equity participation
|
TMC: 100% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
1998
|
October
|
Company established
|
2001
|
January
|
Yaris (1.0 liter) production commenced
|
July
|
Two-shift operation commenced
|
|
2002
|
April
|
Gasoline engine assembly commenced
|
May
|
Yaris (1.3 liter) production commenced
|
|
2003
|
January
|
Diesel engine assembly commenced
|
2004
|
April
|
Internal cross-docking operations commenced
|
May
|
Trials of three-shift production try out (through April 2005)
|
|
2005
|
September
|
Opening ceremony conducted for new training center
|
2006
|
February
|
Three-shift production commenced
|
December
|
Cumulative Yaris production reaches 1 million units
|
|
2008
|
November
|
Engines production discontinued
|
2010
|
August
|
Two-shift operation commenced
|
2011
|
December
|
Three-shift operation re-implemented
|
TMMP
Panoramic view
Overview
Company name
|
Toyota Motor Manufacturing Poland Sp.zo.o.
(TMMP) |
---|---|
Start of production
|
April 2002
|
Site area
|
500,000 m2
|
Business activities & products
|
Production of transmissions and engines; EC60 transmissions for Avensis, Corolla, etc.,
C550 transmissions for Aygo and Yaris, etc., KR engines for Yaris and Aygo, etc. |
Production results for 2011
|
Transmissions: 26,000 units
Engines: 16,000 units |
Number of employees*
|
1,900
|
Equity participation
|
TMC: 94.35% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
1999
|
September
|
Company established
|
2002
|
April
|
Production commenced (transmission case machining and assembly)
|
November
|
Gear shaft machining commenced
|
|
2003
|
January
|
Two-shift assembly commenced
|
February
|
Two-shift machining commenced
|
|
July
|
Gear shaft forging and hub sintering commenced
|
|
2004
|
March
|
Three-shift production commenced (C-type transmissions)
|
2005
|
January
|
Production of KR engines and EC60 transmissions for TPCA (Czechoslovakia) commenced
|
December
|
Three-shift operation commenced (Production of KR engines and EC60 transmissions for TPCA)
|
|
2008
|
September
|
EC60 transmission production commenced
|
November
|
C50 transmission production discontinued
|
TMIP
Exterior view
Overview
Company name
|
Toyota Motor Industries Poland Sp.zo.o.
(TMIP) |
---|---|
Start of production
|
March 2005
|
Site area
|
300,000 m2
|
Business activities & products
|
Engine Production; AD engines for Avensis ,Verso and aulis, ND engines for Yaris
|
Production results for 2011
|
122,000 units
|
Number of employees*
|
880
|
Equity participation
|
TMC: 60% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
2002
|
October
|
Company established
|
2003
|
April
|
Ground-breaking ceremony conducted and plant construction commenced
|
2004
|
January
|
Construction of office and engine plant completed
|
2005
|
March
|
Casting plant completed and production commenced
|
September
|
Plant opening ceremony conducted
|
|
December
|
Casting, large-item processing, and production commenced
|
|
2006
|
April
|
Two-shift assembly commenced
|
2007
|
February
|
Production capacity increased to 15,000 units per month and full production operations commenced
|
2008
|
September
|
One-shift operation commenced
|
2009
|
|
Cumulative engine production reaches 500,000 units
|
2010
|
August
|
1.4 liter diesel engine assembly commenced
|
December
|
Two-shift assembly commenced
|
TCAP
Panoramic view
Overview
Company name
|
Toyota Caetano Portugal, S.A.
(TCAP) |
---|---|
Start of production
|
March 1971
|
Site area
|
Ovar Plant: 310,000 m2
|
Business activities & products
|
Vehicle and vehicle parts assembly
Vehicle production: Coaster, Optimo, Dyna, |
Production results for 2011
|
2,020 vehicles
|
Number of employees*
|
214
|
Equity participation
|
TMC: 27% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
1971
|
March
|
Ovar CKD production plant completed;
Production of Corolla, Corona and Dyna contracted to Tasso commenced at Ovar plant |
1972
|
|
TMC invests in Caetano (27% stake)
|
1978
|
|
Hiace production commenced
|
|
Land Cruiser production commenced
|
|
1979
|
|
Corona production ended
|
1980
|
|
Corolla production ended
|
|
Hilux production commenced
|
|
1982
|
December
|
Optimo (base vehicle: Coaster) production commenced
|
1987
|
|
Hilux 4x4 production commenced
|
1993
|
June
|
Cumulative production of Toyota vehicles reaches 200,000
|
|
Land Cruiser production ended
|
|
1996
|
September
|
Dyna double cab production commenced
|
October
|
Hilux production ended
|
|
2008
|
May
|
ISO 14001 and ISO 9001 certification for vehicle inspection obtained
|
2011
|
December
|
Hiace production ended
|
TMMT
Panoramic view
Overview
Company name
|
Toyota Motor Manufacturing Turkey Inc.
(TMMT) |
---|---|
Start of production
|
September 1994
|
Site area
|
920,000 m2
|
Business activities & products
|
Vehicle production: Corolla Verso, Auris
|
Production results for 2011
|
92,000 vehicles
|
Number of employees*
|
2,563
|
Equity participation
|
TMC: 90% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
1990
|
January
|
Toyotasa established (TMC holds a 40% stake)
|
1994
|
September
|
Corolla Sedan production commenced
|
2000
|
October
|
Toyotasa divides manufacturing and sales, TMMT established
|
2001
|
September
|
All shares of Sabanci in TMMT acquired
|
2002
|
January
|
Corolla sedan exports to Europe commenced
|
March
|
Capital reorganization implemented (TMMT placed under TMEM)
|
|
August
|
Corolla wagon exports to Europe commenced
|
|
2003
|
March
|
Two-shift assembly commenced
|
2004
|
February
|
Corolla Verso production and exports to Europe commenced
|
2005
|
|
Cumulative production reaches 500,000 vehicles
|
2007
|
February
|
Auris production and exports to Europe commenced
|
2009
|
March
|
Cumulative production reaches 1 million vehicles
|
TMUK
Burnaston Plant
Deeside Plant
Overview
Company name
|
Toyota Motor Manufacturing (UK) Ltd.
(TMUK) |
---|---|
Start of production
|
August 1992 (Deeside Plant), December 1992 (Burnaston Plant)
|
Site area
|
Burnaston Plant: 2,350,000 m2
Deeside Plant: 480,000 m2 |
Business activities & products
|
Production of vehicles and engines
Burnaston Plant: Avensis, Auris, and Auris Hybrid production Deeside Plant: ZR engines for the Avensis and Auris etc |
Production results for 2011
|
128,000 vehicles
Engines: 130,000 units |
Number of employees*
|
3,748
|
Equity participation
|
TMC: 100% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
1989
|
December
|
Company established
|
1992
|
August
|
Carina E 4A engine production commenced (Deeside Plant)
|
December
|
Carina E production commenced (Burnaston Plant)
|
|
1994
|
December
|
Carina E 7A engine production commenced
|
1997
|
October
|
Carina E redesigned and Avensis production commenced
|
1998
|
September
|
Corolla Liftback production commenced
|
1999
|
October
|
Corolla Liftback ZZ engine production commenced
|
2000
|
March
|
Production commenced at casting plant
|
December
|
Yaris SZ engine production commenced
|
|
2003
|
January
|
Diesel engines production commenced
|
2007
|
January
|
ZR engines production commenced
|
February
|
Auris (redesigned Corolla) production commenced
|
|
2010
|
May
|
ZR hybrid engine production commenced
|
June
|
Auris Hybrid production commenced
|
TMMR
Panoramic view
Overview
Company name
|
Limited Liability Company "Toyota Motor Manufacturing Russia"
(TMMR) |
---|---|
Start of production
|
December 2007
|
Site area
|
2,240,000 m2
|
Business activities & products
|
Vehicle production: Camry
|
Production results for 2011
|
14,000 vehicles
|
Number of employees*
|
1,349
|
Equity participation
|
TMC: 87% (including affiliates)
|
- *
- As of December 31, 2011
Events
Year
|
Month
|
Events
|
---|---|---|
2005
|
May
|
Company established
|
June
|
Ground-breaking ceremony conducted
|
|
2007
|
December
|
Camry production commenced
|
2009
|
March
|
Camry partially redesigned
|
2011
|
November
|
Camry redesigned
|